A typical house renovation moves from surveys and design to controlled strip-out, structural work, first-fix services, closing up, finishes and handover. The exact order depends on the building, access and whether anyone will remain at home.
Date:
Author:
Aspire Building
001
Resolve the layout before physical work
Agree the room arrangement and establish what the existing building can accommodate. The first part of the programme should allow for investigation, drawings, specialist design, relevant approvals and ordering items with long lead times. A proposed start date needs to account for those dependencies.
Confirm kitchen and bathroom layouts early enough to coordinate drainage, water, ventilation, electrical points and heating. Moving a sink after the floor is closed can affect several trades. The same applies to fitted joinery that hides a socket or prevents access to a valve.
Use the house renovation pre-start checklist to record the scope and outstanding decisions. Before construction, confirm which building regulations approvals apply and who is handling them.


002
Strip out, inspect and complete the concealed work
Strip-out should follow an agreed plan for protection, service isolation, waste and any hazardous materials. It is not an instruction to remove everything. Retained joinery, flooring and fittings need to be identified before the team starts, and unexpected conditions need a clear route for review.
Structural alterations and repairs come before covering the relevant areas. Where the work affects the external envelope, the programme must also provide suitable weather protection. The contractor and designer should agree the sequence, including any temporary support and inspections; this is not a DIY demolition guide.
First fix generally means the services and supporting work that will later be concealed: cables, pipework, drainage routes and related preparation. Coordinate these with partitions, insulation and ventilation. Arrange required checks before boarding or plastering makes the work inaccessible.
The photographs show Aspire’s ongoing Exmouth Market apartment refurbishment, with new partitions and exposed ceilings. The planned layout includes three bedrooms, shared living space, a kitchen, bathroom and separate WC. It remains an ongoing project, not a completed result or a timetable for another home.
003
Close up, allow drying and fit the finishes
Once the relevant concealed work has been checked, the programme can move through boarding, plastering and other preparation. Allow the specified drying and curing conditions before applying finishes. A surface that feels dry is not automatically ready for every flooring or decorating system.
Second fix includes fitting items such as switches, sockets, sanitaryware, doors and trims after the earlier service work and preparation. Kitchen installation, tiling, flooring and decoration need a coordinated sequence specific to the products and room. There is no universal rule that every floor goes down before every kitchen.
Ask who checks the substrate, finished floor levels and product requirements before installation. A change in floor thickness can affect thresholds, doors and appliances. Keep access to service points and protect completed areas from later deliveries and trades.
For example, discuss the bathroom’s fittings, waterproofing system, tile layout and floor build-up together before tiling starts. Those choices are connected even though different people may carry out the work.
004
Plan handover as a stage of the work
Agree what must be complete before each room can be used.
Allow time for testing, commissioning and relevant inspections.
Walk through the agreed scope and record outstanding items.
Collect applicable certificates, product instructions and care information.
Confirm how any remaining items will be resolved and who to contact.
Should you renovate one room at a time? Sometimes, especially when parts of the home need to remain usable. But services may cross several rooms, so completing each room in isolation can mean reopening finished work. Ask for a whole-property plan before agreeing the phases.
How long will it take? A useful programme comes from the actual scope, site conditions, approvals and material availability. Ask which stages depend on the previous one finishing and where decisions are still outstanding, rather than relying on a generic number of weeks.